Northlake II
Ashland, VA

Property Overview
Northlake II is a five-building, two-phase ground up development project in Ashland, VA, approximately 15 miles north of Richmond, VA. With both easy access to and visibility from Interstate 95, the main north-south artery on the east cost, Northlake II is primed to be the premier industrial park in greater Richmond.

Phase 1
Building A: 91,000 SF
Building B: 102,000 SF
Building C: 152,000 SF
Subtotal: 345,000
Phase 2
Building D: 118,000 SF
Building E: 192,000 SF
Subtotal: 310,000 SF
Total: 655,000 SF

Schedule
Phase I
Site Plan Approval: 8/9/2021
Commence Construction: 9/8/2021
Early TI Start: 6/6/2022
Substantial Completion: 9/6/2022
Phase II
Site Plan Approval: 8/17/2022
Commence Construction: 12/1/2022
Early TI Start: 11/8/2023
Substantial Completion: 12/31/2024
Details
Location
Harley Club Drive
Ashland, VA 23005
Driving Directions
Contact / Leasing
JP Matan
(301) 815-9985 (direct)
jpmatan@mataninc.com
Additional Info
Status: Planned
Size: 655,000 SF / 63.00 acres